Bechtel argued that one of three men killed in the April 29 scaffolding collapse had signed an agreement requiring workplace ...
Bechtel Energy responded to the lawsuit tied to the April 29 scaffolding collapse at the Port Arthur LNG construction site, which claimed the lives of three workers.
The Port Arthur LNG Phase 1 project is currently under construction and consists of trains 1 and 2, as well as two LNG storage tanks and associated facilities.
In July 2024, Sempra Infrastructure announced that Bechtel had been selected for a fixed-price engineering, procurement and construction (EPC) contract for the project.
The Port Arthur LNG Phase 1 project is currently under construction and consists of trains 1 and 2, as well as two LNG storage tanks and associated facilities.
A judge has extended a court order preserving the Port Arthur LNG accident scene until May 28.
Bechtel and the sheriff's office are all working together to find out exactly what happened," Holmes said. Port Arthur LNG is a joint project between Sempra Infrastructure and ConocoPhillips.
SABINE PASS, Texas — An industrial accident early Tuesday morning at the Port Arthur LNG site claimed the lives of three Houston-area men and injured two others. It happened around 2 a.m. at the ...
Three workers were killed and two others injured after a scaffolding gave way at a Texas construction site, authorities said. First responders were called to the Port Arthur LNG site early Tuesday ...